01. Confirm the region and
geography of the business site

02. Confirm the meteorological and geographical elements of the region

03. Confirm the power capacity of the utility

04. Confirm the local government ordinance

05. Apply for development permission

06. Obtain permission for development activities

07. Pre-use inspection

STEP 01

Confirm the location and district of the business site.

To generate solar power, it is important to first check the various regulations and permissions regarding the land.
It is important to carefully examine the details of the land such as the area, classification, purpose area, and restrictions.
STEP 02

Geographical elements of this area Check the geographical elements of this area.

Solar power generation means that the more cloudy or rainy days there are, the less power generation there will be.
In addition, it also acts as a factor that reduces efficiency when the surface temperature rises.
The geographical elements of the area are also important.
If the altitude is high or the wind is strong, it must be taken into account when designing the structure in order to achieve stable solar power generation.
It is also necessary to analyze the direction and shadow of the solar power plant.

Google Earth

VWorld (Spatial Information Open Platform)

Weather Maru Solar Power Generation Prediction Information Inquiry

Seoul Solar Map

Haechum Solar Map

Sixthirty

STEP 03

KEPCO Check the capacity

Solar power generation projects require prior confirmation of available capacity as they use KEPCO power lines for power transmission.
The substation transformer and distribution line have a limit to the capacity they can operate.
Depending on the technical review, the connection capacity may be limited, so it is necessary to check in advance if the connection capacity is required.

01

Korea Electric Power Corporation's Distributed Power Capacity Inquiry Service

* You can check with the address or the three-phase power line number of the power plant.

02

Contact the customer service center of KEPCO

* 24-hour Electricity Consultation Customer Service Center

without a country code

123

STEP 04

The local government ordinance must be checked.

Check the local ordinance of the local government using the local government law information system.
STEP 05

Application for Power Generation Permit

It is important to submit an application for a PPA (Power Supply Contract) quickly,
even if you have obtained a generation permit, as the technical review may not be possible.
STEP 06

Permission for Development Activities

01
Submit Application for Development Activity
(Developer)
02
Review Permission for Development Activity
(Approver)
03
Grant, Deny, or Grant with Conditions
(Approver)
04
Carry out Development Activity
(Developer
STEP 07

Before Use Inspectio

Finally, the Korean Electric Stability Corporation will check if the electrical equipment installation and contents are suitable.

Inspection standards

Whether the contents of the electrical equipment installation and modification construction are suitable for the construction plan

The suitability of the inspection procedure or electrical equipment inspection items prescribed by the Minister of Trade, Industry and Energy.